Continuing progress on Warm Springs Power Pathway

Power lines cross a forested valley with snow-capped mountains and blue sky in the distance.
The Bethel-Round Butte power lines were originally built more than 60 years ago, during the early 1960s.WSP&WE/PGE

Warm Springs Power & Water Enterprises continues the hard work at bringing the Confederated Tribes' energy vision to life by moving forward on the Warm Springs Power Pathway Project.

The Project represents an opportunity for the tribes to sustain its people through jobs, educational and generational wealth for the community while also expanding vital regional transmission capacity.

Despite some inaccurate reports over the past year suggesting the $250 million federal grant was targeted for termination, Power & Water and the Confederated Tribes have never received communication from the Department of Energy indicating the award was canceled.

The project has proceeded as planned, a reflection of the tribes' long-standing, mutually respectful sovereign-to-sovereign relationship with the federal government.

The project completed its annual technical review successfully in March 2026, and momentum has only grown since.

The Natural Resources-Resource Management Interdisciplinary Team has approved temporary soil and geologic studies at select locations along the existing Bethel-Round Butte line on the reservation, with tribal monitors and resource protection measures in place throughout to safeguard cultural resources, first foods, wildlife and fisheries.

The project team also launched community engagement planning efforts in August, engaging tribal members and communities along the rest of the line.

Looking ahead, and consistent with the Confederated Tribes' review and approval processes, environmental studies and initial engineering designs continue through 2027, and permitting through 2029. Additional contracting follows in 2027-2028, with construction targeted for 2030 through 2032. If all CTWS and community approval processes receive approval, the project would be expected to be in service in 2032.

The Warm Springs Power Pathway project, with Portland General Electric as the tribes' partner, is a major infrastructure initiative to rebuild and upgrade the approximately 100-mile transmission line, adding significant power capacity, from the source at the Pelton-Round Butte hydro system to the Willamette Valley. The project also involves the installation of high-capacity fiber-optic cables, improving regional broadband.

Most importantly, the project will support tribal sovereignty by greatly expanding economic and employment opportunities for the Confederated Tribes. For more information, and how to stay engaged, visit: warmspringspowerpathway.com

September 2, 2026: the front pageFrom the print editionSeptember 2, 2026, page 1Read the whole edition →

See an error? Tell us · Submit news · Write a letter to the editor

Report a problem

What we send with it

This page and the few pages before it, your device and browser, screen size, whether you're using the app, and the site version. No passwords or personal details.